Certified Authorization Professional – CAP – Question326
There are seven risk responses for any project. Which one of the following is a valid risk response for a negative risk event? A. Exploit B. Share C. Enhance D. Acceptance
Correct Answer: D
Please disable your adblocker or whitelist this site!