Certified Authorization Professional – CAP – Question389

During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?

A.
Symptoms
B. Cost of the project
C. Warning signs
D. Risk rating

Correct Answer: B