Certified Authorization Professional – CAP – Question383

You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project which of the following are likely to increase?

A.
Risks
B. Human resource needs
C. Quality control concerns
D. Costs

Correct Answer: A

Certified Authorization Professional – CAP – Question380

The Information System Security Officer (ISSO) and Information System Security Engineer (ISSE) play the role of a supporter and advisor, respectively. Which of the following statements are true about ISSO and ISSE? Each correct answer represents a complete solution. Choose all that apply.

A.
An ISSE manages the security of the information system that is slated for Certification & Accreditation (C&A).
B. An ISSO takes part in the development activities that are required to implement system ch anges.
C. An ISSE provides advice on the continuous monitoring of the information system.
D. An ISSE provides advice on the impacts of system changes.
E. An ISSO manages the security of the information system that is slated for Certification & Accreditation (C&A).

Correct Answer: CDE

Certified Authorization Professional – CAP – Question379

Harry is a project manager of a software development project. In the early stages of planning, he and the stakeholders operated with the belief that the software they were developing would work with their organization's current computer operating system. Now that the project team has started developing the software it has become apparent that the software will not work with nearly half of the organization's computer operating systems. The incorrect belief Harry had in the software compatibility is an example of what in project management?

A.
Assumption
B. Issue
C. Risk
D. Constraint

Correct Answer: A

Certified Authorization Professional – CAP – Question377

Which of the following processes is described in the statement below? "It is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout the project."

A.
Perform Quantitative Risk Analysis
B. Monitor and Control Risks
C. Perform Qualitative Risk Analysis
D. Identify Risks

Correct Answer: B