Certified Authorization Professional – CAP – Question205

You are the project manager of the GGH Project in your company. Your company is structured as a functional organization and you report to the functional manager that you are ready to move onto the quantitative risk analysis process. What things will you need as inputs for the quantitative risk analysis of the project in this scenario?

A.
You will need the risk register, risk management plan, permission from the functional manager, and any relevant organizational process assets.
B. You will need the risk register, risk management plan, outputs of qualitative risk analysis, and any relevant organizational process assets.
C. You will need the risk register, risk management plan, cost management plan, schedule management plan, and any relevant organizational process assets.
D. Quantitative risk analysis does not happen through the project manager in a functional stru cture.

Correct Answer: C

Certified Authorization Professional – CAP – Question204

The Phase 1 of DITSCAP C&A is known as Definition Phase. The goal of this phase is to define the C&A level of effort, identify the main C&A roles and responsibilities, and create an agreement on the method for implementing the security requirements. What are the process activities of this phase? Each correct answer represents a complete solution. Choose all that apply.

A.
Registration
B. Document mission need
C. Negotiation
D. Initial Certification Analysis

Correct Answer: ABC

Certified Authorization Professional – CAP – Question203

You are the project manager of the GHY project for your organization. You are about to start the qualitative risk analysis process for the project and you need to determine the roles and responsibilities for conducting risk management. Where can you find this information?

A.
Risk management plan
B. Enterprise environmental factors
C. Staffing management plan
D. Risk register

Correct Answer: A

Certified Authorization Professional – CAP – Question202

You are the project manager of a large construction project. Part of the project involves the wiring of the electricity in the building your project is creating. You and the project team determine the electrical work is too dangerous to perform yourself so you hire an electrician to perform the work for the project. This is an example of what type of risk response?

A.
Transference
B. Mitigation
C. Avoidance
D. Acceptance

Correct Answer: A

Certified Authorization Professional – CAP – Question201

You are the project manager of the CUL project in your organization. You and the project team are assessing the risk events and creating a probability and impact matrix for the identified risks. Which one of the following statements best describes the requirements for the data type used in qualitative risk analysis?

A.
A qualitative risk analysis requires fast and simple data to complete the analysis.
B. A qualitative risk analysis requires accurate and unbiased data if it is to be credible.
C. A qualitative risk analysis required unbiased stakeholders with biased risk tolerances.
D. A qualitative risk analysis encourages biased data to reveal risk tolerances.

Correct Answer: B

Certified Authorization Professional – CAP – Question200

Rob is the project manager of the IDLK Project for his company. This project has a budget of $5,600,000 and is expected to last 18 months. Rob has learned that a new law may affect how the project is allowed to proceed -even though the organization has already invested over $750,000 in the project. What risk response is the most appropriate for this instance?

A.
Transference
B. Mitigation
C. Enhance
D. Acceptance

Correct Answer: D

Certified Authorization Professional – CAP – Question199

Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?

A.
At every status meeting the project team project risk management is an agenda item.
B. Project risk management happens at every milestone.
C. Project risk management has been concluded with the project planning.
D. Project risk management is scheduled for every month in the 18-month project.

Correct Answer: A

Certified Authorization Professional – CAP – Question198

The only output of the perform qualitative risk analysis are risk register updates. When the project manager updates the risk register he will need to include several pieces of information including all of the following except for which one?

A.
Trends in qualitative risk analysis
B. Risk probability-impact matrix
C. Watchlist of low-priority risks
D. Risks grouped by categories

Correct Answer: B

Certified Authorization Professional – CAP – Question197

The Phase 4 of DITSCAP C&A is known as Post Accreditation. This phase starts after the system has been accredited in Phase 3. What are the process activities of this phase? Each correct answer represents a complete solution. Choose all that apply.

A.
Maintenance of the SSAA
B. Compliance validation
C. Change management
D. System operations
E. Security operations
F. Continue to review and refine the SSAA

Correct Answer: ABCDE