Certified Authorization Professional – CAP – Question155

Harry is the project manager of the MMQ Construction Project. In this project Harry has identified a supplier who can create stained glass windows for 1,000 window units in the construction project. The supplier is an artist who works by himself, but creates windows for several companies throughout the United States. Management reviews the proposal to use this supplier and while they agree that the supplier is talented, they do not think the artist can fulfill the 1,000 window units in time for the project's deadline. Management asked Harry to find a supplier who will guarantee the completion of the windows by the needed date in the schedule. What risk response has management asked Harry to implement?

A.
Mitigation
B. Acceptance
C. Transference
D. Avoidance

Correct Answer: A

Certified Authorization Professional – CAP – Question154

Penetration testing (also called pen testing) is the practice of testing a computer system, network, or Web application to find vulnerabilities that an attacker could exploit. Which of the following areas can be exploited in a penetration test? Each correct answer represents a complete solution. Choose all that apply.

A.
Race conditions
B. Social engineering
C. Information system architectures
D. Buffer overflows
E. Kernel flaws
F. Trojan horses
G. File and directory permissions

Correct Answer: ABDEFG

Certified Authorization Professional – CAP – Question153

Walter is the project manager of a large construction project. He'll be working with several vendors on the project. Vendors will be providing materials and labor for several parts of the project. Some of the works in the project are very dangerous so Walter has implemented safety requirements for all of the vendors and his own project team. Stakeholders for the project have added new requirements, which have caused new risks in the project. A vendor has identified a new risk that could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk. What should Walter also update in this scenario considering the risk event?

A.
Project communications plan
B. Project management plan
C. Project contractual relationship with the vendor
D. Project scope statement

Correct Answer: B

Certified Authorization Professional – CAP – Question152

Which of the following is NOT a responsibility of a data owner?

A.
Maintaining and protecting data
B. Ensuring that the necessary security controls are in place
C. Delegating responsibility of the day-to-day maintenance of the data protection mechanisms to the data custodian
D. Approving access requests

Correct Answer: A

Certified Authorization Professional – CAP – Question149

You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's schedule performance index?

A.
1.06
B. 0.93
C. -$37,800
D. 0.92

Correct Answer: D

Certified Authorization Professional – CAP – Question148

Gary is the project manager for his project. He and the project team have completed the qualitative risk analysis process and are about to enter the quantitative risk analysis process when Mary, the project sponsor, wants to know what quantitative risk analysis will review. Which of the following statements best defines what quantitative risk analysis will review?

A.
The quantitative risk analysis process will analyze the effect of risk events that may substantially impact the project's competing demands.
B. The quantitative risk analysis reviews the results of risk identification and prepares the project for risk response management.
C. The quantitative risk analysis process will review risk events for their probability and impact on the project objectives.
D. The quantitative risk analysis seeks to determine the true cost of each identified risk event and the probability of each risk event to determine the risk exposure.

Correct Answer: A

Certified Authorization Professional – CAP – Question147

Your project has several risks that may cause serious financial impact should they happen. You have studied the risk events and made some potential risk responses for the risk events but management wants you to do more. They'd like for you to create some type of a chart that identified the risk probability and impact with a financial amount for each risk event. What is the likely outcome of creating this type of chart?

A.
Quantitative analysis
B. Risk response plan
C. Contingency reserve
D. Risk response

Correct Answer: C