Certified Authorization Professional – CAP – Question055

You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's schedule performance index?

A.
1.06
B. 0.92
C. -$37,800
D. 0.93

Correct Answer: B

Certified Authorization Professional – CAP – Question053

Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you. What component of the change control system communicates the approval or denial of a proposed change request?

A.
Configuration management system
B. Change log
C. Scope change control system
D. Integrated change control

Correct Answer: D

Certified Authorization Professional – CAP – Question052

You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?

A.
Risk-related contract decisions
B. Project document updates
C. Risk register updates
D. Organizational process assets updates

Correct Answer: D

Certified Authorization Professional – CAP – Question046

Frank is the project manager of the NHH Project. He is working with the project team to create a plan to document the procedures to manage risks throughout the project. This document will define how risks will be identified and quantified. It will also define how contingency plans will be implemented by the project team. What document is Frank and the NHH Project team creating in this scenario?

A.
Project management plan
B. Resource management plan
C. Risk management plan
D. Project plan

Correct Answer: C