Certified Authorization Professional – CAP – Question025

You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?

A.
Quantitative risk analysis
B. Qualitative risk analysis
C. Requested changes
D. Risk audits

Correct Answer: C

Certified Authorization Professional – CAP – Question023

Your project has several risks that may cause serious financial impact should they happen. You have studied the risk events and made some potential risk responses for the risk events but management wants you to do more. They'd like for you to create some type of a chart that identified the risk probability and impact with a financial amount for each risk event. What is the likely outcome of creating this type of chart?

A.
Risk response plan
B. Quantitative analysis
C. Risk response
D. Contingency reserve

Correct Answer: D

Certified Authorization Professional – CAP – Question020

You are the project manager of the NKJ Project for your company. The project's success or failure will have a significant impact on your organization's profitability for the coming year. Management has asked you to identify the risk events and communicate the event's probability and impact as early as possible in the project. Management wants to avoid risk events and needs to analyze the cost-benefits of each risk event in this project. What term is assigned to the low-level of stakeholder tolerance in this project?

A.
Risk avoidance
B. Mitigation-ready project management
C. Risk utility function
D. Risk-reward mentality

Correct Answer: C

Certified Authorization Professional – CAP – Question019

Ben is the project manager of the YHT Project for his company. Alice, one of his team members, is confused about when project risks will happen in the project. Which one of the following statements is the most accurate about when project risk happens?

A.
Project risk can happen at any moment.
B. Project risk is uncertain, so no one can predict when the event will happen.
C. Project risk happens throughout the project execution.
D. Project risk is always in the future.

Correct Answer: D

Certified Authorization Professional – CAP – Question017

DIACAP applies to the acquisition, operation, and sustainment of any DoD system that collects, stores, transmits, or processes unclassified or classified information since December 1997. What phases are identified by DIACAP? Each correct answer represents a complete solution. Choose all that apply.

A.
Validation
B. Re-Accreditation
C. Verification
D. System Definition
E. Identification
F. Accreditation

Correct Answer: ABCD

Certified Authorization Professional – CAP – Question016

According to U.S. Department of Defense (DoD) Instruction 8500.2, there are eight Information Assurance (IA) areas, and the controls are referred to as IA controls. Which of the following are among the eight areas of IA defined by DoD? Each correct answer represents a complete solution. Choose all that apply.

A.
VI Vulnerability and Incident Management
B. DC Security Design & Configuration
C. EC Enclave and Computing Environment
D. Information systems acquisition, development, and maintenance

Correct Answer: ABC