Certified Authorization Professional – CAP – Question228

Which of the following documents is described in the statement below? "It is developed along with all processes of the risk management. It contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning."

A.
Project charter
B. Risk management plan
C. Risk register
D. Quality management plan

Correct Answer: C