Lisa is the project manager of the SQL project for her company. She has completed the risk response planning with her project team and is now ready to update the risk register to reflect the risk response. Which of the following statements best describes the level of detail Lisa should include with the risk responses she has created?
A. The level of detail is set by historical information.
B. The level of detail must define exactly the risk response for each identified risk.
C. The level of detail is set of project risk governance.
D. The level of detail should correspond with the priority ranking
A. The level of detail is set by historical information.
B. The level of detail must define exactly the risk response for each identified risk.
C. The level of detail is set of project risk governance.
D. The level of detail should correspond with the priority ranking