Certified Authorization Professional – CAP – Question314

You and your project team have identified the project risks and now are analyzing the probability and impact of the risks. What type of analysis of the risks provides a quick and high-level review of each identified risk event?

A.
Qualitative risk analysis
B. Seven risk responses
C. Quantitative risk analysis
D. A risk probability-impact matrix

Correct Answer: A