Which of the following recovery plans includes a monitoring process and triggers for initiating planned actions?

A.
Business continuity plan
B. Contingency plan
C. Continuity of Operations Plan
D. Disaster recovery plan

Correct Answer: B

Tagged Certified Authorization Professional - CAP, Question 357