Certified Authorization Professional – CAP – Question374

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

A.
No, the ZAS Corporation did not complete all of the work.
B. Yes, the ZAS Corporation did not choose to terminate the contract work.
C. It depends on what the outcome of a lawsuit will determine.
D. It depends on what the termination clause of the contract stipulates

Correct Answer: D