Certified Cloud Security Professional – CCSP – Question495
Which of the following is a valid risk management metric? A. KPI B. KRI C. SOC D. SLA
Correct Answer: B
Explanation:
Explanation: KRI stands for key risk indicator. KRIs are the red flags if you will in the world of risk management. When these change, they indicate something is amiss and should be looked at quickly to determine if the change is minor or indicative of something important.