You and your project team have identified the project risks and now are analyzing the probability and impact of the risks. What type of analysis of the risks provides a quick and high-level review of each identified risk event?
A. Quantitative risk analysis
B. Qualitative risk analysis
C. Seven risk responses
D. A risk probability-impact matrix