Secure Software Lifecycle Professional – CSSLP – Question060

You are the project manager of the NNN project for your company. You and the project team are working together to plan the risk responses for the project. You feel that the team has successfully completed the risk response planning and now you must initiate what risk process it is. Which of the following risk processes is repeated after the plan risk responses to determine if the overall project risk has been satisfactorily decreased?

A.
Quantitative risk analysis
B. Risk identification
C. Risk response implementation
D. Qualitative risk analysis

Correct Answer: A

Explanation:

Explanation: The quantitative risk analysis process is repeated after the plan risk responses to determine if the overall project risk has been satisfactorily decreased. Answer: D is incorrect. Qualitative risk analysis is not repeated after the plan risk response process. Answer: B is incorrect. Risk identification is an ongoing process that happens throughout the project. Answer: C is incorrect. Risk response implementation is not a project management process.