Which of the following activities are performed by the 'Do' cycle component of PDCA (plan-do-check-act)? Each correct answer represents a complete solution. Choose all that apply.
A. It detects and responds to incidents properly.
B. It determines controls and their objectives.
C. It manages resources that are required to achieve a goal.
D. It performs security awareness training.
E. It operates the selected controls.
A. It detects and responds to incidents properly.
B. It determines controls and their objectives.
C. It manages resources that are required to achieve a goal.
D. It performs security awareness training.
E. It operates the selected controls.