Secure Software Lifecycle Professional – CSSLP – Question130

In which of the following phases of the DITSCAP process does Security Test and Evaluation (ST&E) occur?

A.
Phase 2
B. Phase 4
C. Phase 3
D. Phase 1

Correct Answer: C

Explanation:

Explanation: Security Test and Evaluation (ST&E) occurs in Phase 3 of the DITSCAP C&A process. Answer: D is incorrect. The Phase 1 of DITSCAP C&A is known as Definition Phase. The goal of this phase is to define the C&A level of effort, identify the main C&A roles and responsibilities, and create an agreement on the method for implementing the security requirements. The Phase 1 starts with the input of the mission need. This phase comprises three process activities: Document mission need Registration Negotiation Answer: A is incorrect. The Phase 2 of DITSCAP C&A is known as Verification. The goal of this phase is to obtain a fully integrated system for certification testing and accreditation. This phase takes place between the signing of the initial version of the SSAA and the formal accreditation of the system. This phase verifies security requirements during system development. The process activities of this phase are as follows: Configuring refinement of the SSAA System development Certification analysis Assessment of the Analysis Results Answer: B is incorrect. The Phase 4 of DITSCAP C&A is known as Post Accreditation. This phase starts after the system has been accredited in the Phase 3. The goal of this phase is to continue to operate and manage the system and to ensure that it will maintain an acceptable level of residual risk. The process activities of this phase are as follows: System operations Security operations Maintenance of the SSAA Change management Compliance validation