What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?

A.
Risk analysis plan
B. Staffing management plan
C. Risk management plan
D. Human resource management plan

Correct Answer: C

Explanation:

Explanation: The risk management plan defines how risks will be identified, analyzed, responded to, and then monitored and controlled regardless of the structure of the organization. Answer: D is incorrect. The human resources management plan does define how risks will be analyzed. Answer: B is incorrect. The staffing management plan does define how risks will be analyzed. Answer: A is incorrect. The risk analysis plan does define how risks will be analyzed.