You are the project manager for a construction project. The project involves casting of a column in a very narrow space. Because of lack of space, casting it is highly dangerous. High technical skill will be required for casting that column. You decide to hire a local expert team for casting that column. Which of the following types of risk response are you following?

A.
Avoidance
B. Acceptance
C. Mitigation
D. Transference

Correct Answer: D

Explanation:

Explanation: According to the question, you are hiring a local expert team for casting the column. As you have transferred your risk to a third party, this is the transference risk response that you have adopted. Transference is a strategy to mitigate negative risks or threats. In this strategy, consequences and the ownership of a risk is transferred to a third party. This strategy does not eliminate the risk but transfers responsibility of managing the risk to another party. Insurance is an example of transference. Answer: C is incorrect. Mitigation is a risk response planning technique associated with threats that seeks to reduce the probability of occurrence or impact of a risk to below an acceptable threshold. Risk mitigation involves taking early action to reduce the probability and impact of a risk occurring on the project. Adopting less complex processes, conducting more tests, or choosing a more stable supplier are examples of mitigation actions. Answer: A is incorrect. Avoidance involves changing the project management plan to eliminate the threat entirely. Answer: B is incorrect. Acceptance response is a part of Risk Response planning process. Acceptance response delineates that the project plan will not be changed to deal with the risk. Management may develop a contingency plan if the risk does occur. Acceptance response to a risk event is a strategy that can be used for risks that pose either threats or opportunities. Acceptance response can be of two types: Passive acceptance: It is a strategy in which no plans are made to try or avoid or mitigate the risk. Active acceptance: Such responses include developing contingency reserves to deal with risks, in case they occur. Acceptance is the only response for both threats and opportunities.