Which of the following rules pertaining to a Business Continuity Plan/Disaster Recovery Plan is incorrect?
A. In order to facilitate recovery, a single plan should cover all locations.
B. There should be requirements to form a committee to decide a course of action. These decisions should be made ahead of time and incorporated into the plan.
C. In its procedures and tasks, the plan should refer to functions, not specific individuals.
D. Critical vendors should be contacted ahead of time to validate equipment can be obtained in a timely manner.
A. In order to facilitate recovery, a single plan should cover all locations.
B. There should be requirements to form a committee to decide a course of action. These decisions should be made ahead of time and incorporated into the plan.
C. In its procedures and tasks, the plan should refer to functions, not specific individuals.
D. Critical vendors should be contacted ahead of time to validate equipment can be obtained in a timely manner.