Which of the following is the most complete disaster recovery plan test type, to be performed after successfully completing the Parallel test? A. Full Interruption test B. Checklist test C. Simulation test D. Structured walk-through test
Correct Answer: A
Explanation:
The difference between this and the full-interruption test is that the primary production processing of the business does not stop; the test processing runs in parallel to the real processing. This is the most common type of disaster recovery plan testing.
A checklist test is only considered a preliminary step to a real test.
In a structured walk-through test, business unit management representatives meet to walk through the plan, ensuring it accurately reflects the organization’s ability to recover successfully, at least on paper.
A simulation test is aimed at testing the ability of the personnel to respond to a simulated disaster, but not recovery process is actually performed.
Source: KRUTZ, Ronald L. & VINES, Russel D., The CISSP Prep Guide: Mastering the Ten Domains of Computer Security, John Wiley & Sons, 2001, Chapter 8: Business Continuity Planning and Disaster Recovery Planning (page 289).