Project Management Professional (PMP) Exam Practice – Question1025 Which quality control technique illustrates the 80/20 principle? A. Ishikawa diagram B. Control chart C. Run chart D. Pareto chart Show Answer Hide Answer Correct Answer: D Post navigation Project Management Professional (PMP) Exam Practice – Question1024Project Management Professional (PMP) Exam Practice – Question1026