Project Management Professional (PMP) Exam Practice – Question1065

When a control chart is used to monitor performance of a process, which of the following will be set by the project manager and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken to prevent exceeding the specification limits?


A.
Upper and lower control limits
B. Upper and lower specification limits
C. Process mean
D. Data points

Correct Answer: A