Project Management Professional (PMP) Exam Practice – Question0102

Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?


A.
Perform Qualitative Risk Analysis
B. Perform Quantitative Risk Analysis
C. Plan Risk Management
D. Plan Risk Responses

Correct Answer: A