Project Management Professional (PMP) Exam Practice – Question1231 The cost benefit analysis tool is used for creating: A. Pareto charts. B. quality metrics. C. change requests. D. Ishikawa diagrams. Show Answer Hide Answer Correct Answer: B Post navigation Project Management Professional (PMP) Exam Practice – Question1230Project Management Professional (PMP) Exam Practice – Question1232