Your project is now under way, and you are working with your team to prepare your requirements management plan. Which of the following strongly influences how requirements are managed?
A. The phase-to-phase relationship
B. A set of procedures by which project scope and product scope may be changed
C. Requirements traceability matrix
D. Requirements documentation