When you review cost performance data on your project, different responses will be required depending on the degree of variance or control thresholds from the baseline. For example, a variance of 10 percent might not require immediate action, whereas a
variance of 100 percent will require investigation. A description of how you plan to manage cost variances should be included in the______________
A. Cost management plan
B. Change management plan
C. Performance measurement plan
D. Variance management plan