Which of the following calculations CANNOT be used to determine EAC?
A. EV to date plus the remaining project budget
B. Accepts actual costs and predicts future ETC work will be done at the budgeted rate
C. Assumes what the program has experienced can be expected to continue
D. ETC will be performed at an efficiency rate considering both the CPI and SPI
A. EV to date plus the remaining project budget
B. Accepts actual costs and predicts future ETC work will be done at the budgeted rate
C. Assumes what the program has experienced can be expected to continue
D. ETC will be performed at an efficiency rate considering both the CPI and SPI