You are managing a project that has five subcontractors. You must monitor contract performance, make payments, and manage provider interface. One subcontractor submitted a change request to expand the scope of its work. You decided to award a contract
modification based on a review of this request. All these activities are part of______________
A. Control procurements
B. Conduct procurements
C. Form contract
D. Configuration management