Schedule control is one important way to avoid delays. While planning and executing schedule recovery, one tool available to you for control schedules is______________
A. Changing the schedule management plan
B. Immediately rebase lining
C. Adjusting leads and lags
D. Changing all project and resource calendars
A. Changing the schedule management plan
B. Immediately rebase lining
C. Adjusting leads and lags
D. Changing all project and resource calendars