Within your company's portfolio, your project is ranked in the top five in terms of importance of the 60 projects under way; however, the number of resources available to you is still limited. You have decided to pilot test the use of critical chain on your project. You
have calculated your critical path. You want to ensure that your target finish date does not slip in the critical chain method. To do so you should______________
A. Add a project buffer
B. Put in three feeding buffers
C. Determine the drum resource
D. Manage the total float of the network paths