You are a project manager leading the construction project of a new garbage incinerator. Local residents and environmental groups are opposed to this project because of its environmental impact. Management agrees with your request to partner with a third
party that will be responsible for providing state-of-the-art "air scrubbers," to clean the exhaust to an acceptable level. This decision will delay the project but will allow it to continue. It is an example of which following risk response?
A. Passive acceptance
B. Active acceptance
C. Mitigation
D. Transference