You are the Project Manager of an engineering project for a cellular base station with a one-year schedule as defined by the project management plan. You need a spectrum analyzer. During the procurement process, you have decided to rent this equipment. The
rental cost is $506 per month.
rental cost is $506 per month.
What type of cost is this?
A. Indirect 
B. Direct 
C. Fixed 
D. Variable