Project Management Professional (PMP) Exam Practice – Question0210 In which process group is the scope first defined? A. Initiating B. Planning C. Executing D. Controlling Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0209Project Management Professional (PMP) Exam Practice – Question0211