A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
A. risk management plan
B. human resource management plan
C. scope management plan
D. procurement management plan
A. risk management plan
B. human resource management plan
C. scope management plan
D. procurement management plan