Project Management Professional (PMP) Exam Practice – Question0425 During what process is the quality policy determined? A. Initiating B. Executing C. Planning D. Controlling Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0424Project Management Professional (PMP) Exam Practice – Question0426