To complete planning, a project manager wants to organize and summarize the projects 1,000 required tests into a manageable list. What tool should the project manage use?
A. Histogram
B. Ishikawa diagram
C. Affinity diagram
D. Control chart
A. Histogram
B. Ishikawa diagram
C. Affinity diagram
D. Control chart