During a projects execution, a previously unidentified stakeholder within the customers organization requests a change that could affect the projects scope. The stakeholders influence within the customers organization is strong.
What should the project manager do first?
A. Schedule a meeting and, based on the outcome, update the project management plan.
B. Issue a change request to the change control board (CCB).
C. Identify the new stakeholder and update the stakeholder register.
D. Meet with all stakeholders to discuss the change.