Project Management Professional (PMP) Exam Practice – Question0763

A company implements a project to design a new product for its current customers. A project scope statement is defined with constraints and assumptions associated with the project objectives.
What should the project manager do next?


A.
Meet with the project team to validate the project scope that will be executed by the team.
B. Work with the project team and key stakeholders to determine the products, services, and/or results to be delivered.
C. Establish a hierarchical breakdown of the total scope to be carried out by the project team to comply with project objectives.
D. Ensure that all requested changes, or the preventive or corrective actions, are included in the project scope.

Correct Answer: B