During the execution of an IT project, a project manager warns of the possibility that the main server may fail due to constant, local-area electrical outages. The project manager signs a contract to rent an additional server from a local company.
What strategy is the project manager using?
A. Share
B. Transfer
C. Mitigate
D. Enhance
What strategy is the project manager using?
A. Share
B. Transfer
C. Mitigate
D. Enhance