A project team identifies several weather-related risks that could delay the project. What should the project manager do to assess the effect on the projects objective?
A. Develop a probability and impact matrix
B. Appoint a resource to monitor weather forecasts
C. Update the risk management plan
D. Use modeling and simulation techniques
A. Develop a probability and impact matrix
B. Appoint a resource to monitor weather forecasts
C. Update the risk management plan
D. Use modeling and simulation techniques