Project Management Professional (PMP) Exam Practice – Question0935 During which process does the project team receive bids and proposals? A. Conduct Procurements B. Plan Procurements C. Estimate Costs D. Control Budget Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0934Project Management Professional (PMP) Exam Practice – Question0936