Which input to the Plan Risk Management process provides information on high-level risks?
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets