Project Management Professional (PMP) Exam Practice – Question0005

Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?


A.
Feedback analysis
B. Stakeholder analysis
C. Communication management plan
D. Stakeholder management plan

Correct Answer: D