Project Management Professional (PMP) Exam Practice – Question0008 An input to Develop Project Charter is a/an: A. Business case. B. Activity list. C. Project management plan. D. Cost forecast. Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0007Project Management Professional (PMP) Exam Practice – Question0009