The process of prioritizing risks for further analysis or action is known as:
A. Plan Risk Management.
B. Plan Risk Responses.
C. Perform Qualitative Risk Analysis.
D. Perform Quantitative Risk Analysis.
A. Plan Risk Management.
B. Plan Risk Responses.
C. Perform Qualitative Risk Analysis.
D. Perform Quantitative Risk Analysis.