Project Management Professional (PMP) Exam Practice – Question0020

The process of prioritizing risks for further analysis or action is known as:


A.
Plan Risk Management.
B. Plan Risk Responses.
C. Perform Qualitative Risk Analysis.
D. Perform Quantitative Risk Analysis.

Correct Answer: C