Project Management Professional (PMP) Exam Practice – Question0021 Stakeholder satisfaction should be managed as a key project: A. Benefit B. Initiative C. Objective D. Process Show Answer Hide Answer Correct Answer: C Post navigation Project Management Professional (PMP) Exam Practice – Question0020Project Management Professional (PMP) Exam Practice – Question0022