Project Management Professional (PMP) Exam Practice – Question0022 Which cost is associated with nonconformance? A. Liabilities B. Inspections C. Training D. Equipment Show Answer Hide Answer Correct Answer: A Post navigation Project Management Professional (PMP) Exam Practice – Question0021Project Management Professional (PMP) Exam Practice – Question0023