Project Management Professional (PMP) Exam Practice – Question0024

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:


A.
Project management plan.
B. Project charter.
C. Work breakdown structure.
D. Stakeholder register.

Correct Answer: B