Project Management Professional (PMP) Exam Practice – Question0033

The zero duration of milestones in project planning occurs because milestones:


A.
Are unpredictable and challenge the Plan Schedule Management process.
B. Occur at random times in the project plans.
C. Represent a moment in time such as a significant project point or event.
D. Represent both significant and insignificant points in the project and are difficult to anticipate.

Correct Answer: C